Banner HR Project Timeline
![]() |
HR Implementation Timeline | HR Training Schedule | ||
| Phase I (1st & 2nd Quarter 2007) | ||||
|
Employee and Position Class Earn Deduction & Leave Codes Define Payroll Calendar & Pay ID |
May 28-31, 2007 | Advanced Position Control (in conjunction with Finance) | ||
| June 5-7, 2007 | HR Specific Conversion Support Session | |||
| June 6-11, 2007 | Self Service | |||
| Phase II (3rd & 4th Quarter 2007) | ||||
| Aug 24, 2007 |
Employee Classes Loaded |
July 30-Aug 3, 2007 | Self Service Time Entry | |
| Aug 27, 2007 | Benefits/Deductions Loaded | Aug 27-31, 2007 | Advanced Training Topics | |
| Sept 28, 2007 | Position Classes Loaded. Rules/Validation Complete. | Oct 1-5, 2007 | Advanced Benefits Training | |
| Oct 11, 2007 | Earn/Leave Codes Loaded | Nov 19, 2007 | HR Progress Assessment | |
| Dec 3, 2007 | Security Set-Up/Design | Nov 26-30, 2007 | Self Service System Design | |
| Dec 31, 2007 | Institutional Changes Approved | |||
| Dec 2007 | Employee Self-Service Complete | |||
| Phase III (1st & 2nd Quarter 2008) | ||||
| Jan 7, 2008 | Job Assignments & Benefits Assignments Loaded | Feb 11-15, 2008 | HR Parallel Testing | |
| April 2008 | Time Entry Complete |
March 10, 2008
|
End User Training Begins | |
| May 2008 | Full System Testing | June 9, 2008 | HR Progress Assessment | |
| Phase IV (3rd & 4th Quarter 2008) | ||||
| Nov 2008 | Interfaces Complete. Final System Testing. HR Parallel Testing | Aug 4-8, 2008 | Solution Validation, Lessons Learned & Consulting | |
| Oct 20-24, 2008 | US Regulatory Reporting | |||
| Nov 17-21, 2008 | Pre Go-Live Support | |||
| Dec 8-12, 2008 | Go-Live Support | |||
| Dec 2008 | End User Training Complete | |||
|
December 2008 HR Go-Live Print January 2009 paychecks |
||||